3. Ownership of instruments of service and re-use of documents
This provision is more relevant to design professionals than to contractors and builders. Contracts generated by AIA provide the design professional retains ownership rights to the design documents and grants the owner only a non-exclusive license to use the drawings on the current project and any alterations and additions to the project. On occasion, an owner may ask to become the ‘owner,’ including copyright owner, of the construction drawings. In such a case, the design professional would lose all rights to the drawings, possibly including the right to re-use original design elements that are non-standard design features.
If confronted with such a request, one should carefully consider future consequences and also consider asking the owner for a waiver and release of all future claims related to the documents, including claims arising on the current project, any future additions or renovations, and entirely different projects. If the owner makes any use of the drawings without retaining and involving the design professional, the owner should indemnify the design professional against claims that arise from such use.
4. Warranty and correction of work
This provision is more relevant to builders and contractors than to design professionals. Many construction contracts contain a provision requiring the contractor to correct, free of charge, any non-conforming work for a period of one year following the date of substantial completion. Sometimes the one-year period is extended for another 12 months with respect to any warranty work performed during the original one-year warranty period, creating a potentially perpetual warranty period. You may wish to push back on this. Sometimes, the requested warranty period is two or even five years, which seems excessively long.
If the owner asks for an extended warranty, you should ask for a provision that specifies should the owner fail to give notice promptly after discovery of the non-conforming condition, or fail to give notice of the condition before the expiration of the warranty period, the owner waives its right to require correction on a free-of-charge basis.
5. Termination of contract for ‘convenience’ and lost profits
Sometimes an owner/client wants the ability to terminate the contract for any or no reason, even if you have done nothing wrong and you are fully in compliance with all contract obligations. This provision could have devastating financial effects. For instance, you may have cleared the decks and turned down other profitable work in order to dedicate resources to the owner’s project. When it is then terminated for no reason, you may incur significant costs in demobilizing and transitioning to your next project.
If the client asks for a contract provision giving the client the right of “termination for convenience,” consider asking for an accompanying provision that provides that, should your contract be terminated without cause and for convenience, you are compensated for your lost profits on the job, which should be specified in the contract to prevent later disagreement. The owner will undoubtedly push back on this—if so, at a minimum you should be paid for all work up to and including the day of termination, as well as reasonable demobilization and transition costs.
In part two of our article, we will examine five additional provisions.
Courtney Moates Paulk is a construction lawyer and chair of Hirschler Fleischer’s litigation section. She advises public and private owners, developers, contractors, and subcontractors on a broad range of business matters and disputes. She is an active member of the Associated General Contractors (AGC), serving on the Richmond District Executive Committee of the Virginia Chapter, and the Contract Documents and AIA-AGC Joint Committees of AGC America. She can be contacted at cpaulk@hf-law.com.
R. Webb Moore, PE, is a construction lawyer and shareholder at Hirschler Fleischer. He is also a licensed professional engineer, licensed patent attorney (admitted to practice in the U. S. Patent and Trademark Office), and a Certified Construction Arbitrator of the American Arbitration Association (AAA). Prior to law school, he worked for four years as a design engineer with a national firm in Roanoke, Virginia. He may be reached at wmoore@hf-law.com.
Great job. Is this the Webb Noore of Richmond, Va.?